    KEPCO facility contribution calculator

    Estimate the contribution paid to KEPCO for an ordinary new connection or capacity increase. The calculation uses the application-date bands in Annex 4 of the 2026-08-01 supply terms, rather than an old online calculator rate. Basic contribution, new-route distance contribution and VAT are shown separately; internal building work is a different cost.

    MAKE IT SIMPLE

    South Korea · standard facility contribution, 2026 Q3 supply terms dated 2026-08-01. Uses Annex 4 rates for applications from 2023-07-01 onward.

    New routes only: overhead free distance 200 m; underground 50 m. Drop fractional metres after subtracting the free distance. Enter 0 when no new-route distance fee applies; do not re-enter an existing already-charged route. Measurement points must be confirmed by KEPCO.

    Low-voltage increases are limited to existing contracts of at least 5 kW, without changing supply conditions. Mixed routes, conductor additions, small-contract exemptions, relocations, temporary/special supplies, internal construction and connection deposits are excluded. VAT is shown separately; this is an estimate, not a KEPCO quotation.

    Calculation basis

    KEPCO supply terms · 2026 Q3, 2026-08-01 · Annex 4 application rates from 2023-07-01.

    Basis reviewed: 2026 Q4 · 21 October. Fee revisions are not applied automatically.

    Result

    Worked examples

    New low-voltage overhead; 10 kW; no distance charge

    KRW 911,000 + VAT 91,100 = 1,002,100

    306,000 + (10−5) × 121,000 is the basic contribution.